Project area: the total area of the original classroom is about 168 square meters;
Grooming teaching area is about 56 square meters, bathing teaching area is about 56 square meters (including a small foster area)
The teaching area of cat Grooming is about 56 square meters;
Equipment budget: USD 95,000 (excluding construction costs of water and electricity transformation, classroom partition, etc.);
Working station:
Grooming teaching area: 1 teacher station + 1 assistant teacher station + 30 student working stations;
Bath teaching area: 1 spa teaching station + 8 bathing teaching stations + 1 set of large drying equipment;
Cat Grooming teaching area: 1 teacher station + 1 assistant teacher station + 18 student working stations
Estimated power consumption: the power consumption of teaching equipments is about 70kW, and that of air conditioning, lighting, water heater is about 70kW.
Figure 1 (original drawing)
Figure 2 (front view)
Figure 3 (front view)
Figure 4 (overall perspective)
Figure 5 (overall perspective)
Figure 6 (3D rendering of Grooming teaching area)
Figure 7 (3D rendering of Grooming teaching area)
Figure 8 (3D rendering of bathing teaching area)
Figure 9 (3D rendering of bathing teaching area)
Figure 10 (3D rendering of cat Grooming teaching area)